Friday, 26 March 2010

Pilers return to site


This week, Rock and Aluvium, have been back on site for the second phase of the piling work. This should be complete by early next week.

The work on the ground beams is progressing well.

We have made good progress with the MUGA pitch. The tarmac was laid at the end of last week and the fencing around it has been put up this week. The rubber surface will be put in place next week.

We have been busy preparing for the school frames to be delivered in a couple of weeks.

Don't forget - if you want to know what is happening right now you can view our live webcam

Monday, 22 March 2010

site developments


This is how things are looking at the minute, but for an even more precise update, log on to the live web link and see what is happening right now!

Friday, 12 March 2010

Setting steel works


This week we have been concreting the ground beams and setting the bolts of the steel frames in place, in preparation for the pillars.


You may remember some of the students had a visit from piling specialists Rock and Alluvium, who are carrying out the piling work for the building. Their next visit is due to take place in a couple of weeks so we have been busy preparing the site for this.


Don’t forget to log onto our live web-cam to see what is happening on site right now.


Friday, 5 March 2010

Things are beaming

Friday 5th March

We have been progressing with the construction of the ground beams, which form the foundations of the building. There is a lot of work to be done, which we’ll be busy with over the coming weeks.

You may have noticed the road sweepers around the site, who have been doing their best to keep the grounds outside the school clear during the mud shift. Local residents will have received the latest newsletter from Bardsley’s, keeping them up to date on what is happening.

Over the coming weeks we will be focusing on completing the MUGA pitch (Multi Use Games Area).

If you want to check out the latest developments on site, log on to our live web cam. http://88.96.131.206:2500/view/index.shtml

Wednesday, 3 March 2010

Big Brother is watching!

Our live web cam is now up and running so you can watch what is happening on site 24/7!

Friday, 26 February 2010

Rise to the surface


This week we have completed works to Constablee Primary School’s playground. The contractors have finished creating the footpath by the side of it.

One of the big jobs we faced was to level out the playing field at Constablee School by raising the surface. The school had a visit from OFSTED this week, and Bardsley’s ensured the building work didn’t affect it and that road sweepers were on site.

One of the biggest jobs we have been working on is the piling rig, which forms the foundations of the building. Some of our students were given a presentation by piling specialists Rock and Alluvium who carried out the work with Bardsley’s. It was a great chance for the students to find out more about the work that goes into the construction and see how things are coming along.

Next week, we will be continuing with laying the foundation work, which we are hoping to complete by the middle of next month.

Friday, 19 February 2010

Sod cutting ceremony marks start of construction work


19 February 2010

We have had a busy few weeks and made some great progress. The construction work has started and we marked it with an official sod-cutting ceremony, which was attended by our Head Boy and Girl, Robert Pratt and Katherine Lucas.

One of the biggest tasks we faced was the sewer diversion works – there was a deep drain running through the school which had to be reconfigured. We were under pressure to do it quickly though before the pilers were delivered to the site for the foundation work to be started. The bad weather also had an impact, but the piling work has now commenced.

As it has been half term this week, we have focused on extending the work to Constablee Primary School’s playground whilst the pupils are off. We have completed it and put a temporary fence up around it. Our next job is to recreate a footpath for access off the field.

An exciting development about to get under way is the erection of the steel frame, which will form the skeleton of the building. This week we had a positive meeting with Rossendale steel firm James Killelea & Co, based in Crawshawbooth. They are producing a 3D model of the steel work for us, which will be displayed on site. We will let you know when it is complete.

We will also continue to keep you updated on the site developments, but if you do have any issues or concerns about the building work, then please contact us on site on 01706 222870. We will deal with your enquiry as soon as possible.