Showing posts with label MUGA. Show all posts
Showing posts with label MUGA. Show all posts

Friday, 23 April 2010

Taking shape

You have probably noticed the steel work is progressing very well since we started last week. Our building is already starting to take shape – it’s very exciting!

Next week we will be commencing with the pre-cast staircase. The MUGA pitch should be ready to be handed over very soon once the final layers of sand have been delivered and put in place.

Don’t forget to log onto our live web cam for the latest happenings on site.

http://88.96.131.206:2500/view/index.shtml

Friday, 16 April 2010

Steel yourselves…..big developments have happened!



James Killelea & Sons delivered the steel work this week, and our contractors have already got to work on erecting it.

Things will really start to take shape now – we’ll soon to able to see the size of our Sixth Form, which is very exciting. This is going to be the main focus on site over the coming weeks. We will be able to bring the metal steel work in for the building’s floors shortly.

As we reported last week, we had to delay laying the astra-turf on the MUGA pitch, but this has now been completed. The MUGA pitch will soon be ready, but the next stage is to sand the surface. Let’s hope the weather stays on our side!

We will be soon getting to work on the internal drainage, but we’ll bring you more on that next week.

Don’t forget to log on to our live webcam to watch the latest events on site.