Friday, 16 April 2010

Steel yourselves…..big developments have happened!



James Killelea & Sons delivered the steel work this week, and our contractors have already got to work on erecting it.

Things will really start to take shape now – we’ll soon to able to see the size of our Sixth Form, which is very exciting. This is going to be the main focus on site over the coming weeks. We will be able to bring the metal steel work in for the building’s floors shortly.

As we reported last week, we had to delay laying the astra-turf on the MUGA pitch, but this has now been completed. The MUGA pitch will soon be ready, but the next stage is to sand the surface. Let’s hope the weather stays on our side!

We will be soon getting to work on the internal drainage, but we’ll bring you more on that next week.

Don’t forget to log on to our live webcam to watch the latest events on site.

Friday, 9 April 2010

Things moving along well


Whilst the school has been enjoying the Easter break, the contractors have been making good progress on site.

The foundations are almost complete, and the steel work programme is set to commence next week. Some of our students paid a visit to James Killelea and Company Ltd last week to watch the steel being made.

Elsewhere, we are still working on our new MUGA pitch. We have been set back a few days though because of the weather, which has meant we had to postpone laying the astra-turf on top of the rubber pad.

Friday, 26 March 2010

Pilers return to site


This week, Rock and Aluvium, have been back on site for the second phase of the piling work. This should be complete by early next week.

The work on the ground beams is progressing well.

We have made good progress with the MUGA pitch. The tarmac was laid at the end of last week and the fencing around it has been put up this week. The rubber surface will be put in place next week.

We have been busy preparing for the school frames to be delivered in a couple of weeks.

Don't forget - if you want to know what is happening right now you can view our live webcam

Monday, 22 March 2010

site developments


This is how things are looking at the minute, but for an even more precise update, log on to the live web link and see what is happening right now!

Friday, 12 March 2010

Setting steel works


This week we have been concreting the ground beams and setting the bolts of the steel frames in place, in preparation for the pillars.


You may remember some of the students had a visit from piling specialists Rock and Alluvium, who are carrying out the piling work for the building. Their next visit is due to take place in a couple of weeks so we have been busy preparing the site for this.


Don’t forget to log onto our live web-cam to see what is happening on site right now.


Friday, 5 March 2010

Things are beaming

Friday 5th March

We have been progressing with the construction of the ground beams, which form the foundations of the building. There is a lot of work to be done, which we’ll be busy with over the coming weeks.

You may have noticed the road sweepers around the site, who have been doing their best to keep the grounds outside the school clear during the mud shift. Local residents will have received the latest newsletter from Bardsley’s, keeping them up to date on what is happening.

Over the coming weeks we will be focusing on completing the MUGA pitch (Multi Use Games Area).

If you want to check out the latest developments on site, log on to our live web cam. http://88.96.131.206:2500/view/index.shtml

Wednesday, 3 March 2010

Big Brother is watching!

Our live web cam is now up and running so you can watch what is happening on site 24/7!