Friday 21 May 2010

Decking out the site


















IT has been a glorious week and we’ve made great progress on site. We have finished laying the metal decking on the first and second floors, and we’ll soon be putting the next set of staircases in place.

The bricklaying will commence next week, which is set to take approx 10 weeks to complete. The roof materials are also being brought in next week so we will be getting to work on that.


Friday 14 May 2010

Latest on site developments

There’s plenty going on at the moment on site and our Sixth Form building is really starting to take shape.

The steel foundations of the building have now been completed and the first of the three main staircases has been put in place.

Over the next few weeks work on the under floor drainage will take place. We have started laying the metal decking on the floors – which will be concreted over when its finished.

We’re preparing for the brick-layers to arrive on site shortly, and we’ll start importing the roof materials next fortnight.

Elsewhere, we have cleared some trees near the school fields to make room for the allotments, which the horticultural students will look after. Work to the school cycle path has also started, which will run alongside of the cemetery and field.

Thursday 6 May 2010

Just look at things now!





In the past couple of weeks, there has been huge developments on site. The steel foundations have been laid and the staircase has been put in place. Have a look at the pictures and see how things are shaping up....