On with the floors and walls

On site, the contractors have been preparing to set the floors for the second phase of the build – which will take place on Tuesday and Wednesday of next week.

Things are really taking shape - we have commenced with putting the pre-cast walls on the external parts of the build. We have made great progress and have already completed 50 percent of it – and we’ll be continuing with this over the next couple of weeks.

Elsewhere, work to the roof is also progressing well. Overall, things are coming along really well – have a look at our live webcam and see what’s happening right now. http://88.96.131.206:2500/view/index.shtml

Friday 4 June 2010

Raise the roof

Things are going really well and excellent progress has been made. We have made up the two weeks we lost at Christmas as a result of the bad weather.

We have started the roof work on the first section of the building and prepping the ground floor slabs on this section.

The drainage and structure work is continuing on site.