Friday 26 March 2010

Pilers return to site


This week, Rock and Aluvium, have been back on site for the second phase of the piling work. This should be complete by early next week.

The work on the ground beams is progressing well.

We have made good progress with the MUGA pitch. The tarmac was laid at the end of last week and the fencing around it has been put up this week. The rubber surface will be put in place next week.

We have been busy preparing for the school frames to be delivered in a couple of weeks.

Don't forget - if you want to know what is happening right now you can view our live webcam